The Arnone Report: Bi-partisan team work yields success with Shark River project

By Monmouth County Freeholder Tom Arnone

Freeholder Tom Arone

Freeholder Tom Arnone

After a very long period time and with many notable road blocks and obstacles, I, along with a great team of my colleagues, including Senator Jennifer Beck (R-11), and Neptune Committeeman Randy Bishop, am so happy to announce that the New Jersey Department of Transportation’s (NJDOT’s) Office of Maritime Resources has awarded the bid to complete the Shark River dredging project. The project’s contract was awarded to Mobile Pumping & Dredging Co., of Chester, PA.

This huge step forward is a result of years of work coordinating with the many agencies that have authority over this project. After being involved in this project for more than fifteen years as Mayor of Neptune City and now as a member of the Board of Chosen Freeholders, I am personally very happy to see this project finally begin.  I have worked with other officials throughout the years whom were also very passionate about this project, including Tom Catley, former Mayor of Neptune Township, as well as other past mayors of the surrounding towns and those in office today. The County has long continued to work cooperatively with these local officials, as well as state and government agencies to move this dredging project forward.

This is a large project, with approximately 106,000 cubic yards of material to be dredged.  With cooperation from the Monmouth County Reclamation Center, which is able to accept and reuse the dredged material, and the Monmouth County Board of Chosen Freeholders providing funding, we have made this project a reality. Not one part of the Shark River project was easy or simple, but we found a way to accomplish this.

Read the rest of this entry »

Posted: September 28th, 2015 | Author: | Filed under: Monmouth County, Neptune, Neptune Township, Shark River | Tags: , , , , , , , , , | 1 Comment »

Shark River Dredging Contract Awarded

11350584_1030419283658703_4977899953030200993_nThe New Jersey Department of Transportation’s Office of Maritime Resources has awarded the bid to complete the long awaited Shark River and Shark River Spur Dredging Project to the low bidder, Mobile Pumping & Dredging Co., of Chester, PA. MPD’s bid of $7,649,817.50 was $1.8 million lower than the next closest bidder.

The State of New Jersey will contribute over $5 million to the project. Monmouth County will contribute $1.1 million and Neptune Township has committed $450,000.  Belmar, Neptune City and Wall Township are expected to share the remaining costs of the project, according to a statement isssued by Senator Jennifer Beck,  Freeholder Tom Arnone and Neptune Township Committeeman Randy Bishop.  Beck said the project will start this year, “if all the stars align,” and will be completed by the end of 2016.

“After over two decades, there has finally been a bid awarded to dredge Shark River. Notably, The National Marine Fisheries only allows dredging work from July 1st to December 31st, so I’m happy to see this monumental step taken forward, which, if all the stars align, will allow dredging to begin this year. None of this could have been possible without the work of Freeholder Tom Arnone and Committeeman Randy Bishop, working together in a bipartisan fashion with every state, county, and local stakeholder to make this project happen. While the State is investing more than $5 million, the project couldn’t have moved forward without the assistance of Monmouth County, which is accepting the material at its landfill and helping to fund the trucking. In addition, a number of surrounding municipalities have preliminary agreed to share in the cost of the project” said Beck.

Read the rest of this entry »

Posted: September 26th, 2015 | Author: | Filed under: Monmouth County, Monmouth County News | Tags: , , , , , , , , , , , , , , , | 2 Comments »